Estates and Facilities
The majority of the carbon emissions included in the 2040 target come from the NHS buildings. For new buildings compliance with the NHS Net Zero Building standard is required. The Estates Net Zero Carbon Delivery plan applies to existing buildings.
KGH has occupied the same site at the edge of Kettering since 1895. The site has a mix of buildings ranging in age from the 1970s to the present day. Most of the clinical services are provided at this site. The age of the buildings along with the confined nature of both internal and external infrastructure place a strain on the capital monies available, which also must pay for compliance, asbestos and fire related works. All services within the Estates and Facilities departments are carried out by KGH employees and the site is fully owned by KGH.
Carbon emissions from energy, water, waste and f-gases are included in the 2040 net zero emissions targets. All other purchases to build and maintain buildings, as well as provide catering, domestic and portering services are included in the 2045 net zero target.
The NHS Net Zero Buildings Strategy and Clinical Waste Strategy also inform the content of this section of the Sustainability Plan.
Where we are now:
To date emissions from buildings have remained approximately static, as shown in Figure 1
Figure 1 Carbon emissions from buildings
The Trust also commissioned a decarbonisation plan during 2023 in order to determine the options for the remaining emissions from buildings. Within the plan were the next steps available and potential routes for funding as this would not be covered by the standard capital monies allocated.
Clinical waste segregation has moved towards the 2026 target, with 60% now moved into the offensive waste stream, partially meeting the NHS target, with 25% in the incineration waste stream and 15% in the orange bag (alternative treatment) waste stream. See Figure 2 below. The Trust has facilities to recycle card, batteries, metal and food as separate waste streams, and has implemented dry mixed recycling in most areas across the site with 150 new bins installed in 2025. The Trust has a dedicated Waste Officer.
Figure 2 Clinical Waste Segregation
Our aims are to:
- Reduce carbon emissions from buildings by 41% with the completion of the new energy centre
- Reduce electrical and heating demand through optimisation the Building Management system
- Increase understanding
- Achieve the NHS segregation targets with 20% of waste in the infectious waste stream
- Increase trust recycling levels to above 50% of non-clinical waste
- Reduce emissions from waste by 50%
- Reduce overall waste levels by 25%
- Reduce water consumption by 10%
- Make reuse rather than purchase the default option
- Create a biodiversity strategy for the site
Action |
Financial Investment |
When |
Responsible Department |
Write full costed heat decarbonisation plan for the site | Medium | 2026 | Estates |
Develop a fully costed plan to install renewable energy technologies and battery storage | Medium | 2026 | Estates |
Review BMS Settings against occupancy | Low | 2026 | Estates |
Implement minimum refurbishment standards from the carbon management plan | Medium | 2026 | Estates |
Ensure Sustainability Impact Assessments are included in all capital projects | Low | 2025 | Estates |
Write a demand reduction plan for water, electricity and heat | Low | 2027 | Sustainability |
Remove the highest Global Warming Potential gases from air conditioning equipment | Medium | 2027 | Estates |
Create an energy policy | Low | 2026 | Sustainability |
Replace belt driven fans with EC fans | Medium | 2027 | Estates |
Replace petrol gardening equipment with electric | Medium | 2027 | Estates |
Create a biodiversity strategy for the site | Low | 2026 | Sustainability |
Install low water use toilets in areas of high use | Medium | 2027 | Estates |
Introduce WarpIt for reuse of items | Low | 2026 | Waste / Sustainability |
Create a repair shop for small repairs to put equipment back into circulation | Low | 2026 | Waste |
Include requirements for take back of electrical equipment within procurement contracts | Low | 2026 | Procurement |
Create online training content for waste segregation | Low | 2025 | Waste |
Review methodologies for calculation of waste emission figures and calculate accurate figure | Low | 2025 | Waste |
Measurement
Energy and water consumption figures from invoices
Waste weights from invoices
Reuse data from online reuse platform
Purchasing data from procurement
f-gas register