Energy Centre Timeline

The building work and the laying of new cables will cause some disruption to traffic flows around the hospital in the coming months and we apologise for that in advance. We appreciate your patience and co-operation as we embark on this important project.

Together, we are not only building a better KGH but also laying the foundations for a healthier, more sustainable future for our community

February 2025 - May 2025

Site Establishment: hoarding and fencing installation, cabins and welfare.

March 2025 - July 2025

Enabling works: temporary generator installation, existing generator building demolition, drainage diversion and retaining walls.

July 2025 - March 2027 

High Voltage Building - leveling and foundations, structural and internal building works, roof finished and mechanical, electrical, and plumbing fit-out.

July 2025 - March 2027 

Energy Centre Building - leveling and foundations, structural and internal works, front of a building, chimney, roof, mechanical, electrical, and plumbing and fit-out.

January 2027 - March 2027

Decommission steam system, phased out heating changeover and completion. 

Summer 2027

New Energy Centre work complete.